First-time energization and third-party MOPs
The challenge
Bringing power distribution online for the first time across a live construction campus, where every step had to be safe, sequenced and approved before work began.
What we did
Developed a full set of energization MOPs: one for each power distribution unit, plus separate MOPs for the subsystems it serves, including the chiller plant and chilled water pump VFD panels, power cooling modules, data hall cooling fans, mechanical UPS systems and power distribution feeding the data hall.
The result
David and the MOP team he leads on site have written 1,600+ MOPs, covering first-time energizations, subsystems and live, turned-over spaces. Other trades took notice: the team now writes MOPs for four to five other contractors on site and for the owner's operations team.