Track record

Problems solved, systems delivered

Live figures from an active 300 MW hyperscale campus, and still counting. Client names are withheld.

Data centers

Hyperscale campus

Work performed as site technical leader and MOP developer, as a subcontractor to a commissioning firm.

MOP development

First-time energization and third-party MOPs

1,600+ MOPs

The challenge

Bringing power distribution online for the first time across a live construction campus, where every step had to be safe, sequenced and approved before work began.

What we did

Developed a full set of energization MOPs: one for each power distribution unit, plus separate MOPs for the subsystems it serves, including the chiller plant and chilled water pump VFD panels, power cooling modules, data hall cooling fans, mechanical UPS systems and power distribution feeding the data hall.

The result

David and the MOP team he leads on site have written 1,600+ MOPs, covering first-time energizations, subsystems and live, turned-over spaces. Other trades took notice: the team now writes MOPs for four to five other contractors on site and for the owner's operations team.

EPMS

EPMS device configuration

~800 breakers · 300+ meters

The challenge

Hundreds of smart breakers and power quality meters had to report accurate data to the site controllers, BMS and EPMS before turnover.

What we did

Configured and validated nearly 800 smart breakers and 300+ power quality meters, including communications settings and meter setup, with every device's settings, readings and data points documented.

The result

Dozens of configuration issues caught and corrected during validation, before they could reach the owner's operations team.

Networks

Low-voltage network configuration

Verified from end device to BMS

The challenge

Reliable communications in a high-noise electrical environment, across a campus-scale power distribution system.

What we did

Supervised communications cable installation methods for high-noise environments, set up the industrial Modbus TCP networks, assigned IP addresses and configured gateways so local controllers and the BMS could read the registers they need.

The result

Documented, validated communications from the site's power distribution equipment to the site controllers and BMS.

Chiller plant

Chiller plant startup

90+ chillers · 130+ pumps

The challenge

Starting up a campus-scale chiller plant safely, in sequence and alongside the manufacturer's startup team.

What we did

Co-developed the startup MOPs for the chillers and chilled water pumps with their VFDs, working with the chiller manufacturer's startup team. Each startup was sequenced, permitted and documented to the same standard as the site's energization MOPs.

The result

Startup MOPs covering 90+ chillers and 130+ chilled water pumps, and still counting.

Earlier work

20 years of solving hard problems

Highlights from industrial automation work before our data center focus.

Rescue and migration

A 200-foot hangar door, offline for six months

At a major international airport, a hangar door more than 200 feet wide had been offline for six months. We had it working in under 48 hours, then replaced its legacy controls, 100+ I/O points, with a modern platform.

Rescue

Saving a one-of-a-kind machine

A custom cutting saw at a major specialty metals forge had been down for months. The original builder's engineer was gone, other integrators had failed and a replacement had a 12-month lead time. By reverse-engineering the system and interviewing current and former operators, we restored full automatic production and kept the forge running.

Controls and BMS

A chiller plant, programmed from scratch

Wrote the complete control logic for a chiller plant, staging chillers, compressors, chilled and hot water pumps and boilers up and down, and built the Ignition-based BMS front end.

Process skids

Zero issues at startup, without a site visit

Commissioned large heater treater and desalter units before they shipped to overseas clients. They started up with zero issues, with no site visit needed.